Update 22.06.2025: The works on the swimming pool have been completed. We are currently awaiting the allocation of water for commissioning, which we have been promised until the end of June 2025.
Update 14.06.2025: A late delivery of the grout has further delayed the opening of the swimming pool. We are currently assuming that the swimming pool can be used again in the course of the coming week.
Update 02.06.2025: The renovation of our swimming pool will be completed this week as planned. However, we will probably not receive the water for filling before 15 June 2025. We currently assume that the swimming pool can be used again on 17 June 2025.
Update 25.05.2025: The renovation of our swimming pool will take about 10 days longer. We currently assume that the pool can be used again before 7 June 2025.
From 21 April 2025 to 30 May 2025 the basin in the swimming pool of Apartamentos Miranda will be renovated. For this purpose, the water will be drained on 18 April 2025 and put back in around 28 May 2025.
The accommodation at Apartamentos Miranda will be open for stays during this period. However, the swimming pool will not be available to our guests during this time.